Job number CN-07-1162046
Ordered new conservatory build and kitchen and bathroom conversion in Sept 2020 .It is now 25 Oct 2021 and conservatory not yet finished .Kitchen not yet installed and bathroom not yet plumbed in or anything fitted .This was caused by a 6 month delay by Leekes Surveyor not forgetting to send plans for planning permission to Newport Borough Council. This has had knock on effects on the whole build . I have emailed board member and General manager without reply. It unacceptable once paid for plans for them not to be submitted as promised . We are now in winter without cooker facilities. Conservatory or kitchen unusable. Yet Leekes are still asking for further stage payments when the stages haven't been completed.
Also measurements by surveyor on build are incorrect resulting in not able to have 60cms dishwasher or double sink as planned .Other problems also too numerous to mention
Please can somebody help